Blue zuma project

Table of Content

The ARC Company specializes in developing and selling a wide range of high-quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC’s president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower. The Project Priority Matrix for the Blue Zuma Project is:

Time Scope Cost
Constrain X
Enhance X
Accept X
Part 1
You are a member of a project team assigned to develop the new razor scooter code named “Blue Zuma.” Table A2.5 contains the information necessary to create a project schedule. For the purpose of this case assume the following: 1. The project begins January 2, 2008.

This essay could be plagiarized. Get your custom essay
“Dirty Pretty Things” Acts of Desperation: The State of Being Desperate
128 writers

ready to help you now

Get original paper

Without paying upfront

2. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.

3. If a holiday falls on a Saturday, then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off. 4. The project team works eight-hour days, Monday through Friday. Construct a network schedule for this project and prepare a memo that answers the following questions:

1. When is the project estimated to be completed? How long will the project take? 2. What is the critical path for the project?
Computer Project Exercises 631
3. Which activity has the greatest amount of slack?
4. How sensitive is this network?
5. Identify two sensible milestones and explain your choices. 6. Compare the advantages/disadvantages of displaying the schedule as a network versus a
Gantt chart.
Include the following printouts:
• A Gantt chart.
• A network diagram highlighting the critical path.
• A schedule table reporting ES, LS, EF, LF, and slack for each activity. Part 2
The following personnel have been assigned to the Blue Zuma project team: • 4 marketing specialists
• 4 design engineers
• 4 development engineers
• 4 industrial engineers
• 1 purchasing agent
Use the file from Part 1 and the information contained in Tables A2.5 and A2.6 to assign resources to the project schedule.
ID Task Name Duration Predecessors Resources
1 Product development project
2 Market analysis 25 days Marketing (4)
3 Product design 40 days 2 Marketing (1) Design (4)
Development (2) Industrial (1)
Purchasing (1)
4 Manufacturing study 20 days 2 Industrial (4) Development (2) 5 Product design selection 10 days 3,4 Marketing (2) Design (3) Development (2) Industrial (2)
Purchasing (.25)
6 Detailed marketing plan 15 days 5 Marketing (4)
7 Manufacturing process 30 days 5 Design (1) Development (2) Industrial (4) 8 Detailed product design 50 days 5 Marketing (2) Design (4) Development (2) Industrial (2) Purchasing (.25)
9 Test prototype 10 days 8 Design (3) Development (2)
10 Finalized product design 25 days 7,9 Marketing (2) Design (3) Development (3) Industrial (2)
11 Order components 7 days 10 Purchasing (1)
12 Order production equipment 14 days 10 Purchasing (1)
13 Install production equipment 35 days 11F-S 1 20 days,
12F-S 1 40 days Development (3) Industrial (4) Design (1)
14 Celebrate 1 day 6,13 Development (4) Industrial (4)
Design (4) Marketing (4) Purchasing (1)
Part A
Prepare a memo that addresses the following questions:
1. Which if any of the resources are overallocated?
2. Which activities involve overallocated resources?
3. Assume that the project is time constrained and try to resolve any overallocation problems by leveling within slack. What happens?
4. What is the impact of leveling within slack on the sensitivity of the network? Include a Gantt chart with the schedule table after leveling within slack. Part B
Prepare a memo that addresses the following questions:
1. Assume that the project is resource constrained and no additional personnel are available. How long will the project take given the resources assigned? (Hint: Undo leveling performed in Part A before answering this question.) Note: No splitting of activities is allowed.

2. How does the new duration compare with the estimated completion date generated from Part 1? What does this tell you about the impact resources can have on a schedule?
Include a Gantt chart with a schedule table depicting the resource-constrained schedule.
Part 3
Top management is not happy with the resource-constrained schedule generated at the end of Part 2. Robin Lane, the president, has promised retailers that production of the new scooters would start on February 1, 2009.

1. What options are available to meet this new deadline if the project is not resource constrained?
2. What options are available to meet this deadline if the project is resource constrained?
Dewey Martin, director of product development, has managed to make the following personnel available to work on specific activities on the project. Since there is an acute shortage of personnel at ARC he requests that you only use additional manpower that will help meet the new deadline. Your
objective is to develop a schedule which will satisfy the deadline with minimum additional resource usage. The available personnel and impact on activity duration are presented in Table A2.7.

Resource $/hour Number Available
Marketing specialist $60 4
Design engineer $90 4
Development engineer $80 4
Industrial engineer $70 4
Purchasing agent $50 1
Appendix 2 Computer Project Exercises 633
Prepare a memo that addresses the following questions:
1. Which additional personnel assignments would you choose to complete the project before the February 1st deadline? Explain your choices as well as the reasons for not choosing other options.
2. How have these changes affected the sensitivity of the network? Include a Gantt chart with a schedule table presenting the new schedule. Note: You cannot go back and relevel resources. These new resources are only available for the stated specific tasks according to the schedule created at the end of Part 2.

Part 4
Robin Lane and top management have approved the schedule generated at the end of Part 3. Save the file containing this schedule as a baseline schedule. Prepare a memo that addresses the following questions:

1. How much is the project estimated to cost?
2. What activity is estimated to cost the most to complete?
3. What resource commands the greatest total cost?
4. During which month of the project are the highest and lowest costs expected to occur? What are those costs?
5. What likely costs are not contained in this budget?
Include a table containing the estimated costs for each activity and a cash flow schedule for each month of the project.
Part 5
Today’s date is August 16, 2008. Table A2.8 summarizes the information regarding activities accomplished to date.
Robin Lane has requested a written status report for the Blue Zuma project. 1. Your status report should include a table containing the PV, EV, AC, BAC, EAC, SV, CV, and CPI for each activity and the whole project. The report should also address the following questions:

Activity Additional Resources Revised Duration Estimates
Detailed marketing plan Marketing (2) 10 days
Detailed product design Design (1) Development (1) 42 days
Install production equipment Industrial (1) Development (1) 27 days TABLE A2.7
Blue Zuma Project
Crashing Options
Pay rates for additional personnel: Marketing, $70/hour; Design, $100/hour; Development, $90/hour; and Industrial, $

Cite this page

Blue zuma project. (2016, Oct 10). Retrieved from

https://graduateway.com/blue-zuma-project/

Remember! This essay was written by a student

You can get a custom paper by one of our expert writers

Order custom paper Without paying upfront